Hog Slat Inc. Newton Grove, NC USA March 2022 12 Evaporative Cooling System Tank Installation Instructions 13. Begin by gluing (1) of the 10” PVC endcaps onto the bottom of Sump Tee. Allow glue to cure completely before in ground installation. 14. Dig roughly a 15” diameter hole 12” from the end of the trough. See Image below. Dig to a depth of roughly 38” below the top of the trough support brackets. Add/remove material until bottom of tank is supported where the 8” connection is in line with the trough. 15. Clean, prepare, and glue the tank onto the assembled PVC trough. 16. Back fill around the tank to secure. Ensure tank remains free of debris during this step.
RkJQdWJsaXNoZXIy MTA3MzU=