Hog Slat - Plastic Flooring System Instruction Manual

Hog Slat Inc. Newton Grove, NC USA May 2024 5 Plastic Flooring System Construction Requirements Verify there is a minimum bedding surface or ledge of 2.0” (51 cm) as shown in Figures 4 & 5. This is where the load gets transmitted to the basic structure. (Note: This minimum required surface will apply regardless if floor is laid on a cement ledge or on top of concrete floor.) Figure 4: Walkway Figure 5: Wall Ledge If flooring is laid on ledge as shown in Figure 6, height of the total construction of the beam, end cap, and flooring should always be slightly lower than level of the concrete walkways or surfaces. This will prevent animals from lifting up the flooring. The ledge should also have at least a 2” minimum bedding surface to allow for the end cap to fit properly. Figure 6: Walkway with ledge